2. Review of existing railway
Market and Passenger Demand
The line is used primarily by a
mix of commuters both within the Island, most importantly across to Portsmouth
by ferry, and to a limited extent beyond to London; by residents for leisure
journeys, and for holiday makers and day tourists for trips from the mainland,
and thence within the Island on holiday.
A key feature of Island Line is
its role as a contributory feeder to/from the mainland, primarily the main line
to Waterloo. Nearly half of Island Line passengers travel via the ferry at Pier
Head. Approximately half the Portsmouth-Ryde ferry passengers use Island line
along the pier. Overall on Island Line passenger demand in July/August is over
three times higher than that in January/February. The classic Saturday to
Saturday holiday traffic using ferries via Ryde Pier Head during school summer
holidays, after decades of slow decline, appears to have stabilised in recent
years at over 10,000 passengers on peak Saturdays.
A period of Island
Line passenger decline in the first half of the 1990's has been stabilised with
evidence of modest traffic growth in recent years.
Train
Service
To achieve the existing Passenger Service Requirement service
level of two trains per hour, the service interval is currently skewed to 20/40
minute intervals each hour, rather than a regular 30 minute clockface headway,
as a result of the constraints of existing rationalised single line
infrastructure at the southern half of the line and provision by two diagrams in
traffic.
Train services attempt to connect with every ferry at Pier
Head. The constraints described above severely constrain the timing of trains
to optimise connections with ferries and connections are too tight to be robust
as ferry services can often run a little late, especially in the summer, due to
conflicting traffic in the Harbour at Portsmouth, on the Solent, or adverse sea
conditions.
On high summer Saturdays previous practise of operating a
more frequent service together with a pier shuttle train to augment the Shanklin
service had been discontinued for a number of years with reports of overcrowding
at peak times when train connections are missed. A third Ryde Pier - Shanklin
train per hour has run on peak summer Saturdays in 2001 with Wight Link
funding.
Train service provision at two trains per hour throughout the
year is similar in level to that during the winter for much of the last three
decades. On summer Saturdays however this service level represents a
significant reduction from past decades, driven by reductions in demand and in
ferry operations.
Based on passenger counts carried out during the
Saturday of the late August Bank Holiday weekend 2001, and observations on
Saturdays in June 2001, we have assessed that a train service incorporating 12
vehicles per hour of capacity would be required for existing demand
levels.
Rolling Stock
The existing vehicles are former
London Underground 1938 tube stock, brought over to the Island in 1989/90,
converted to operate on the 3rd rail DC electrification system. This
initial fleet of eight 2-car sets has been reduced marginally to leave seven
2-car sets on the Island of which one is out of commission and off-lease, having
not been put through the most recent programme of heavy repair. Rolling stock
is maintained at Ryde St Johns depot, including overhaul, with support from
LUL's Acton Works who supply spares and recondition key components.
The
present rolling stock appears to be quite acceptably reliable, and maintainable
with the railway industry in its present form. The proposed fragmentation of LUL
may reduce the part that LUL is able or willing to play in keeping the fleet
running, or it might simply increase their prices.
Damage has been
caused by flooding in autumn/winter 2000 to both rolling stock and depot
equipment. This problem affected a wider area of residential and commercial
property and although not usually as severe as last year, can occasionally
present a problem, not only to the operability of the depot, but also of the
railway through Ryde St Johns with running lines flooded.
The current
rolling stock does suffer from rough riding and bogie component wear. This is
considered to be due at least partly to permanent way condition.
Based on
our experience and discussions with those currently responsible for maintenance
of the fleet, and the LUL rolling stock engineer, we have established
assumptions for this strategic evaluation concerning the cost and longevity of
the existing fleet in operational service. Heavy repair will be required by
2004 and again in 2009. The cost of this heavy repair is likely to escalate on
each occasion given the obsolete components involved. Our view is that it would
be a reasonably robust assumption that the existing fleet can be kept
operational until 2014, i.e. for two further heavy overhauls. Beyond then it is
unlikely that component support for further heavy repair would be available. In
any event subject to the timing of availability of more ex LUL rolling stock,
cascade replacement is likely to become the economic solution assuming that
vehicles can be purchased at little more than scrap value.
Infrastructure
Overview
The existing
infrastructure has been rationalised since the introduction of electric traction
in 1967 and now allows a 20-minute regular interval service between Ryde Pier
Head and Shanklin, a distance of 8.4 miles. The maximum line speed is 45 mph and
existing Class 485 rolling stock has a vehicle weight of 27.5t and a gross
weight of 31.5t. Based on the existing service, the Track Category is 5 and the
Route Availability is 1.
The southern half of the Island Line was
rationalised and resignalled approximately 10 years ago with Brading and Sandown
signal boxes closed, track singling through Brading to Sandown, and with double
track retained at Sandown station as a passing loop with hydrokinetic points.
The single line section between Smallbrook and Sandown is not track circuited
but is signalled by IOW tokenless block. The section south of Sandown is
similarly tokenless and operated on a one train in section basis. After
rationalisation up to three trains per hour (20 minute headway) can be
accommodated on this southern section.
The section of the line north
of Smallbrook is double track unidirectionally signalled with track circuit
block to a crossover north of Ryde Tunnel just south of Ryde Esplanade station.
From this trailing crossover south of Esplanade station to the Pier Head the
route is signalled as two bi-directional lines, one line is only configured for
a 'pier shuttle' train, latterly only required on high summer Saturdays, and is
currently not used.
The infrastructure on the island is leased to the
operator, a situation unique on the British railway network. A 25 year lease
between the landlord, Railtrack plc, and the lessee, Island Line Limited,
governs the responsibilities for maintenance and renewal of the infrastructure
since 1994. Island Line is responsible for the maintenance of the infrastructure
generally e.g. track, signalling, electrification equipment and buildings,
however Railtrack is responsible for the maintenance of structures, earthworks
and the formation below 450mm from the underside of the sleepers. Railtrack is
responsible for renewals except permanent way and the non-structural elements of
stations.
Permanent Way
Two thirds of the 10.4 track miles
of permanent way are flat bottom rail and the remainder of bullhead rail. There
are ten switch and crossing units on the running lines together with two sets of
traps. All the units are bullhead with the exception of a set of traps. The
track is laid generally on shingle ballast although recent maintenance has used
imported limestone ballast. No significant track renewals appear to have been
undertaken over the last six years, although rail on the Pier has been replaced
this year following identification of excessive chair gall. Generally track
condition is typical of minor lines and the existing policy of piecemeal renewal
can continue to meet the requirements of the existing service indefinitely,
subject to the continuing availability of materials, particularly bullhead
switch & crossing components.
Structures
The
structures comprise Ryde tunnel, Ryde pier, Esplanade station structure, 8
underbridges, 9 overbridges, 7 side of line bridges, 6 footbridges, 3 subways,
and 3 culverts. Ryde Pier according to Railtrack is currently assessed to be in
sound condition (RA 10). Ryde Esplanade station supporting structure was
examined during 1999 and expenditure on the substructure is planned within the
next three years. Subject to normal maintenance e.g. painting and re-pointing,
it is unlikely that the major structures will need to be reconstructed during
the next thirty years, however it is probable that it will be necessary to
replace the superstructures of three cattle creeps over this period. With regard
to the overbridges, although some repair works are evident to the arches, it is
probable that all of them can continue to be maintained in the long term.
However, the intermediate supports to the concrete bridges in the Ryde area
could require significant road vehicle derailment protection works. Rowborough
Road Bridge suffers from regular road vehicle collision damage to its parapets
due to poor road alignment on the approaches and works will be required to
strengthen the parapets. The footbridges at Ryde St. Johns and Brading have been
reconstructed recently, and two further footbridges will probably need to be
reconstructed during the next thirty
years.
Earthworks
There are two locations where cuttings
and embankments present problems. At Rowborough the embankment is unstable and
has regularly been subject to temporary speed restrictions. Investigations to
determine appropriate remedial measures are in hand to achieve stabilisation of
the site. At Sandown there is an unstable cutting slope which Railtrack propose
to regrade.
Signalling
Signalling maintenance is the
responsibility of Island Line and renewal the responsibility of Railtrack. All
the signalling is controlled from the signal box at Ryde St. Johns Road. The
interlocking has had numerous major alterations during its life, principally at
the time of electrification in 1966/67 and subsequently in association with
schemes to abolish the other signal boxes and rationalise track layout. The
Sandown interlocking has received only minor alterations since installation in
1986. Recent work has included a major service of the mechanical locking and in
1999/2000 the replacement of outdoor equipment in the Ryde area and the
installation of a new 48-core cable in trough between Ryde Esplanade and
Sandown. An Automatic Train Protection substitute has been provided on the line
by modifying and reactivating the LT trainstop equipment fitted to the trains
and providing the necessary lineside equipment interlocked with the existing
signalling.
A Railtrack review in 1997 reported that the mechanical
locking frame had received recently a 10 yearly service and the electrical
locking was also in good condition and being regularly serviced. At that time
there were no known problems with spare parts for the lever frame, locking tray
and electrical controllers for the foreseeable future. During 1999/2000,
outdoor equipment in the Ryde area was replaced and a new 48-core cable was
installed in trough between Ryde Esplanade and Sandown. A recent Inspection
Report for Stagecoach Island Line describes the signalling equipment as being in
a generally good condition and well maintained. However, wire degradation has
been reported in location cupboards and is being managed currently by spot
replacement of individual wires. In a similar manner the deterioration of the
location boxes is being managed by spot repairs. A number of issues have been
identified in earlier reports which suggest that investment will be required to
replace equipment that is becoming life expired including the 27 core cable,
wiring in location boxes, and relays, and on the structure of Ryde Relay
Room.
Telecoms
Railtrack undertook a survey of the
communications systems in 1995 to consider their condition and anticipated life.
The customer information and public address systems at Ryde Pier Head and
Esplanade were installed in 1991 with a ten-year life subject to maintenance in
the aggressive environment. The signal post telephone system and communications
power supplies were installed in 1992 again with an estimated ten-year life.
Other equipment is of a minor nature and can be replaced on an as-required
basis.
Electrification
The Isle of Wight system is
electrified on the third rail 630v dc system and the supply equipment, which was
originally installed in 1967, is considered to be unique on the network. The
power supply system comprises three substations located at Ryde, Rowborough and
Sandown fed directly from a 33kV supply through fault thrower switches and
associated auto isolators. Each substation has a 630 volt traction rectifier and
transformer unit connected to a dc switchboard of medium speed circuit breakers.
The system is controlled from Eastleigh electrical control room. In general,
Island Line is responsible for maintenance and Railtrack for renewal of the
electrification equipment.
An overview of the condition and future
investment requirements of the electrification equipment has been obtained from
a condition audit undertaken for Railtrack, together with a recent audit of
equipment for Stagecoach Island Line. The outdoor equipment includes the
conductor rail, insulating pots, connecting cables, hookswitches, bonds and
negative reinforcement. Reports identify routine maintenance items and do not
identify any requirement for major investment in the foreseeable future. This is
reasonable given the nature of the equipment.
The original audit of the
substations recorded a number of defects that were assumed to be due to the lack
of planned maintenance although major remedial works appeared to have been
carried out to a high standard. Railtrack's Table of Projected Maintenance and
Renewal Expenditure included in the lease provisionally allowed for renewal
expenditure on certain dc switchgear and transformer/rectifiers by 2004. Recent
reports confirm that regular inspections are being undertaken and do not
identify any imminent major renewal works.
Buildings
Although no details of the existing condition of
the buildings are available, Railtrack anticipated expenditure on Ryde Esplanade
and St. John's stations by 2011. As discussed above, a recent inspection has
confirmed the requirement for extensive remedial works to the supporting
structure at Esplanade station. A proposal for a new transport interchange
terminal at the Ryde Esplanade would replace the existing main station building.
The development of this scheme is at an early stage but is being developed by
IOW Council with implementation by 2004/5. It is assumed that the scheme would
be entirely local authority / external grant funded and that no significant
provision should be assumed to be made by Railtrack for this scheme. In
addition, a scheme has been identified for Park and Ride facilities at Ryde St
John's station.
Summary
Railtrack summarised the future
anticipated works in the lease document based on continuing like-for-like
renewal of the existing assets in modern equivalent form. Expenditure by
Railtrack appears to broadly follow the predicted average although not
necessarily on the predicted items. Examination of the various reports and
subsequent discussions with Island Line, their consultants and Railtrack have
confirmed that this is a reasonable strategy based on the status and utilisation
of the line. However, development of our own Base Case suggests that track
renewals expenditure on the present basis will be insufficient to maintain a
steady state throughout the whole duration of the lease from Railtrack.
Therefore there is concern that this approach, combined with fragmentation of
responsibilities defined in the Lease, could lead to short term solutions to
maintenance and renewal expenditure potentially detrimental to infrastructure
condition in the long term.