4.5 Selection of strategic options for review
From the significant number of available choices we have established the
following conclusions from the evaluation of each key parameter of choice as
follows:
4.5.1 Train service choices
We concluded in
assessing the train service choices (Section 4.1) that:
• In the
case of the Ryde - Ventnor services, the half-hourly service performs better
than the hourly in terms of economic contribution. Given that no additional
infrastructure is required to run half hourly, the half-hourly option is carried
forward to the detailed appraisal for the Ventnor route.
• In every
other train service case considered the hourly service performs better in terms
of economic contribution than the half-hourly service. Given that hourly
services would, if anything, trigger less infrastructure cost (e.g. fewer
passing loops), the hourly options are carried forward to the detailed option
appraisal for the Ryde-Newport route and possible extension to Cowes.
• Service provision from Ryde to Ventnor, Ryde to Newport and
possibly on to Cowes may be worthwhile depending on the scale of the
infrastructure costs involved. However, all options running services along the
Shanklin - Newport axis via a new south chord at Smallbrook give significant
negative economic results whether services extend to Cowes and / or Ventnor or
not. Such services via Smallbrook south chord are therefore rejected at this
stage.
• There would appear relatively little to chose between the
three routing options to and through Newport on annual benefit / operating cost
grounds, and therefore the selection from these three for the Ryde - Newport
option depends on the results from the infrastructure assessment and outlay
estimates.
4.5.2 Rolling stock choices
We concluded in
assessing the rolling stock choices (Section 4.2) that:
• The most
economic rolling stock provision for the Shanklin to Ventnor route would be to
operate ex LUL tube stock as an extension of the existing Ryde to Shanklin
service, rather than incurring the higher costs of diesel or new build overhead
pick-up electric vehicles and associated infrastructure and depot costs.
• Services on the Ryde - Newport route would be operated with
purpose built diesel railcars given the likelihood that Her Majesty's Railway
Inspectorate (HMRI) and the IoW steam railway themselves would be very unlikely
to approve electrification on a preserved steam heritage line on safety grounds.
Furthermore electrification equipment may detract from the heritage
ambience.
• HMRI approval would be significantly more difficult to
achieve for light rail street tramcars rather than for conventional railcar
multiple unit vehicles, when considering the case of joint running on the
preserved heavy rail route between Smallbrook and Wootton. This is principally
in terms of the likely consequence in the event of collision.
4.5.3
Route infrastructure options
We concluded the following in our
infrastructure works assessment (Section 4.4):
• Our preliminary
feasibility assessment favours provision of a terminus at Newport (Barton)
adjacent to Victoria Road. This view is based on cost, on minimising vehicular
and pedestrian conflict with a segregated way, and on providing the opportunity
for extension of IoW steam operation into Newport.
• The
alternative of developing a new alignment from Fairlee to provide a terminal at
Newport Quay is assessed to require a £2m additional outlay and would
achieve similar passenger benefits. It would require a level crossing across
the main road. It would require street running light rail tramcars, given the
significant number of service roads encountered and the joint use of the
quayside itself by road vehicles. Indeed on market days the quay area can
become rather congested with pedestrian and vehicular traffic.
• The option to extend with street running into a Newport town
centre reverse loop would require the Quay route option and is assessed at a
£6m additional outlay compared with the terminus option at Newport Barton
with modest additional passenger benefit.
4.5.4 Selected
options
Therefore we have selected the following three options
comprising potentially compatible combinations of infrastructure, rolling stock,
and train service specification. These have been developed for the purposes of
this report, to assist in the examination of the likely case for the route
reopening. Options 2 and 3 are mutually exclusive:
• Option
1: Half-hourly extension of Ryde Pier Head - Shanklin 3rd rail
ex LUL tube electric trains to Wroxall and Ventnor;
• Option
2: Provision of hourly diesel train Ryde Pier Head - Newport (Barton)
terminus over extended steam railway; or
• Option
3: Provision of hourly diesel light rail tramcars Ryde Pier Head - Cowes
with street running in Newport and Cowes
We have some reservations
concerning the feasibility of Option 3 but have included it to show the results
of the economic evaluation of that route.